Land & Preconstruction

Understand the land before designing the home

Views can inspire the project, but access, easements, utilities, jurisdiction and physical site conditions determine what deserves deeper study.

Views can inspire the project, but access, easements, utilities, jurisdiction and physical site conditions determine what deserves deeper study.

01

Confirm legal access and recorded rights

Do not treat a visible driveway or well-traveled road as proof of legal access. Review title materials and recorded documents with qualified legal and title professionals. Identify access, utility, conservation, shared-drive, maintenance and other easements that may benefit or burden the property. The Teton County easement guide explains why location, language, beneficiaries and obligations all matter.

02

Establish reliable site information

Current boundary and topographic information gives the design and engineering team a common base. Ask a qualified surveyor what work is appropriate for the property and project. Existing improvements, access, grades, water features, vegetation, utility evidence and other conditions may need to be located. Public maps are useful research tools but are not boundary surveys or legal opinions.

03

Investigate utilities and servicing

Identify the likely source, route, capacity, approvals, timing and ownership of water, wastewater, power, communications and other services. A line near the property does not by itself establish connection rights, capacity or cost. Ask who will verify each service and which assumptions belong in the early budget.

04

Study terrain, soils, water and access

Slope, excavation, drainage, groundwater, soils, rock, winter access and staging can affect design and construction. A property-specific team may recommend civil, geotechnical, environmental or other study. Also examine how construction vehicles, deliveries and emergency access would reach the site—not only how the finished driveway will look.

05

Identify jurisdiction and current rules

Determine whether the property falls within the Town of Jackson or unincorporated Teton County and whether other authorities, covenants or review bodies apply. Verify current zoning, overlays, dimensional rules, process and submittal requirements from official sources and qualified professionals. Regulations and interpretations can change.

06

Turn findings into a go/no-go record

Create a written issues list that assigns each open question to a responsible professional, expected source and decision date. Separate verified facts from assumptions. Feed the resulting site-work, utility, approval and consultant allowances into the Build Cost Planner, then update them as real information arrives.

Use this guide to organize questions—not replace professional advice.

Property conditions, regulations, contracts and project requirements vary. Verify current information with the governing authority and qualified legal, design, engineering, title and construction professionals.

Common questions

Planning questions to ask early

Is a county GIS map the same as a survey?

No. Public GIS is useful for research and orientation, but it is not a boundary survey, title report or legal opinion.

Why review easements before design?

An easement’s location and terms can affect access, utility routing, maintenance obligations, privacy and where improvements may be practical.

Can nearby utilities be assumed available?

No. Proximity does not establish capacity, permission, connection route, timing or cost. Verify each service with the appropriate provider and professionals.